Had a big pour in Tacoma where the crew insisted on using a 5 inch slump mix for a driveway, said it would finish faster. It bled out so bad we were troweling soup for an hour.
3 comments
Log in to join the discussion
Log In3 Comments
claire_ramirez221mo ago
Yeah, the "finish faster" line used to make sense to me. But after seeing a few jobs turn to soup and dust, I learned a proper slump is cheaper than a callback.
8
taylor9292mo ago
Oh man, that's brutal! Sounds like they were trying to finish a driveway and ended up making cement soup instead. Hope you at least got paid by the hour for that troweling marathon.
5
charlie_fisher452mo ago
Was the slump even tested on site or did they just trust the ticket? I've seen guys add gallons of water to a 5 inch mix trying to make it "workable", which just turns the cream into a river. Bet the surface was dusting by the next morning too.